Utility installation was completed by Roach
Construction .
Water and sewer main installation for Phase 1
Installation of electric, phone, cable and natural gas service for phase 1.

Roadway base was prepared by Roach Construction and the curb work was completed by Eisinger Construction. HERCO Inc. completed the paving of phase 1 of the subdivision.



Tthe electrical service was connected and the street lights
were installed.
Construction of the first house was
also started..


Entry landscaping was installed

Second house being built and foundation for third house completed.

Third house under construction September 2011